  3. Installation of the shaping sand machine

Installation of the shaping sand machine

Date:2025-08-29 Author:

The crusher should be leveled during installation to make its main shaft perpendicular to the horizontal plane

A lifting device should be set above the crusher, with its capacity considered based on the maximum weight of the crusher's components. Sufficient lifting space should be left the crusher, and appropriate space should be left on one side for maintenance.

Machine commissioning

Before leaving the factory, the crusher has undergone 8 hours of empty operation, and all parts are normal. However, after the crusher is installed on site, a comprehensive inspection should still be carried out.

Check whether the lubricating oil pipes are securely connected, and refill with oil before the test run.

Check the connection of each part, which should be firm and reliable. Carefully check whether there are any objects on the impeller, and if there are, they should be removed promptly.

Check whether the motor wiring is correct and whether the voltage is normal [380V 5%].

Before installing the belt, start the motor first. The rotation should be consistent with the direction indicated on the crusher's nameplate [i.., looking from the feed port, the impeller rotates counterclockwise]. If it is opposite to the nameplate direction, the motor wiring should be adjusted to make rotation consistent with the nameplate direction. It is strictly forbidden to rotate in the opposite direction.

For a double-motor drive, the main shaft assembly is connected to the two motors with the same number of V-belts. The tension of the V-belts on both sides should be adjusted to be the same and straight.

After the inspection correct, before handing over to production, first carry out empty load and load test runs. Only after confirming there are no problems during the test run can it be handed over to production